Progress Summary (Oct 7 - Nov 29)

Completes Progress:

  • Final target: 13,223 (per budget) Overall project target number
  • Expected progress (at 119.1/day x 39 days): 4646 Target number we should have reached by now (daily target × days elapsed)
  • Current total: 672 Actual cumulative number achieved so far
  • Current achievement rate: 14.5% Achievement rate for current period (current total / expected progress)
  • Progress to final target: 5.1% Progress percentage towards final target (current total / final target)
  • Current daily average: 18.3 completes/day Average daily rate calculated using linear regression
  • Gap from daily target: 100.8 completes/day Difference between target daily rate and current daily rate
  • Required catch-up rate: 174.3 completes/day Daily rate needed from now to reach final target by deadline

Eligibles Progress:

  • Final target: 2,729 (per budget) Overall project target number
  • Expected progress (at 24.6/day x 39 days): 959 Target number we should have reached by now (daily target × days elapsed)
  • Current total: 150 Actual cumulative number achieved so far
  • Current achievement rate: 15.6% Achievement rate for current period (current total / expected progress)
  • Progress to final target: 5.5% Progress percentage towards final target (current total / final target)
  • Current daily average: 4.4 eligibles/day Average daily rate calculated using linear regression
  • Gap from daily target: 20.2 eligibles/day Difference between target daily rate and current daily rate
  • Required catch-up rate: 35.8 eligibles/day Daily rate needed from now to reach final target by deadline

Trend Projection Note: